Budgets and variance analysis

The idea

A budget is a financial plan for revenue or costs over a period. Historical budgets use last year's figures; zero-based budgets start from nothing and justify each item. Variance is the difference between budgeted and actual figures: favourable if it increases profit (higher revenue or lower costs), adverse if it reduces it.

  1. Variance == actual −- budget.
  2. Revenue above budget or costs below budget: favourable.
  3. Revenue below or costs above: adverse.

Watch out A cost that is higher than budgeted is adverse, even though the number is bigger.

See it worked

Worked example

Budgeted costs £40 000, actual £43 000. Is the variance favourable or adverse?

  1. Costs are £3000 above budget.
  2. This reduces profit.
  3. Adverse variance of £3000.

Answer £3000 adverse

Your turn

Question 1Calculator allowed2 marks

Budgeted sales revenue is £75 000 and actual revenue is £71 500. What is the size of the variance, in £?

Question 21 mark

Actual material costs are lower than budgeted. The variance is:

Choose one
Question 32 marks

Give one benefit of zero-based budgeting.

Write your answer, then see a model answer
  1. Name the benefit.
  2. Explain it.

Answer Every spending item must be justified from scratch, so wasteful spending carried over from previous years is cut.

A-level Business Pro, Pearson Edexcel 9BS0

A-level Business Pro

£119 once

Price rises to £199 on 1 January. Save £80 by joining before then.

At least 12 months of access

By paying you agree to our Terms and get access straight away, which ends your 14-day cancellation right.

No VAT is charged.

Independent practice for Pearson Edexcel A-level Business (9BS0), not endorsed by Pearson.

Privacy · Terms