A factory makes 12 000 units a week with 40 workers. Find labour productivity.
- .
- units per worker per week.
Answer 300 units per worker per week
A-level Business revision · Theme 2: Managing finance and resources
Production methods are job (one-off), batch (groups) and flow (continuous mass production). Cell production organises workers into teams. Labour productivity output ÷ number of workers (or hours). Higher productivity lowers unit costs and improves competitiveness. Capital-intensive production uses more machines; labour-intensive more workers.
Watch out Higher output does not mean higher productivity if more workers were added.
A factory makes 12 000 units a week with 40 workers. Find labour productivity.
Answer 300 units per worker per week
A team of 25 workers produces 4 500 units a day. What is the labour productivity, in units per worker per day?
Which production method suits a wedding dressmaker making unique gowns?
Explain one way a business could raise labour productivity.
Answer Training workers improves their skills, so they produce more in the same time, lowering unit costs.