Critical path analysis

The idea

Critical path analysis plans a project's activities in a network, showing which must follow others. The earliest start time (EST) and latest finish time (LFT) are calculated. Activities with zero float are on the critical path: any delay to them delays the whole project. Total float == LFT −- duration −- EST.

  1. Work forwards for ESTs, taking the largest when paths join.
  2. Work backwards for LFTs, taking the smallest.
  3. Total float == LFT −- duration −- EST; zero float means critical.

Watch out When paths merge, the earliest start is the largest of the incoming finish times.

See it worked

Worked example

Activity B has EST 4, duration 3 and LFT 10. Find its float.

  1. Float =10−3−4= 10 - 3 - 4.
  2. =3= 3 days.

Answer 3 days

Your turn

Question 1Calculator allowed2 marks

Activity D has an earliest start time of 6, a duration of 5 and a latest finish time of 11. What is its total float, in days?

Question 2Calculator allowed2 marks

Activities A (3 days) and B (5 days) both start at day 0 and must both finish before C can start. What is C's earliest start time, in days?

Question 31 mark

What does it mean if an activity is on the critical path?

Choose one

A-level Business Pro, Pearson Edexcel 9BS0

A-level Business Pro

£119 once

Price rises to £199 on 1 January. Save £80 by joining before then.

At least 12 months of access

By paying you agree to our Terms and get access straight away, which ends your 14-day cancellation right.

No VAT is charged.

Independent practice for Pearson Edexcel A-level Business (9BS0), not endorsed by Pearson.

Privacy · Terms