Activity B has EST 4, duration 3 and LFT 10. Find its float.
- Float .
- days.
Answer 3 days
A-level Business revision · Theme 3: Decision-making techniques and influences
Critical path analysis plans a project's activities in a network, showing which must follow others. The earliest start time (EST) and latest finish time (LFT) are calculated. Activities with zero float are on the critical path: any delay to them delays the whole project. Total float LFT duration EST.
Watch out When paths merge, the earliest start is the largest of the incoming finish times.
Activity B has EST 4, duration 3 and LFT 10. Find its float.
Answer 3 days
Activity D has an earliest start time of 6, a duration of 5 and a latest finish time of 11. What is its total float, in days?
Activities A (3 days) and B (5 days) both start at day 0 and must both finish before C can start. What is C's earliest start time, in days?
What does it mean if an activity is on the critical path?