A-level Business revision · Theme 3: Decision-making techniques and influences

Decision trees

The idea

Decision trees map choices (square nodes) and uncertain outcomes (circle nodes) with probabilities and financial results. The expected value of an outcome node == sum of (probability ×\times value). Net gain == expected value −- cost of the choice. Choose the option with the highest net gain.

  1. Multiply each outcome's value by its probability.
  2. Add them for the expected value.
  3. Subtract the cost to get the net gain; compare options.

Watch out Probabilities at each chance node must add up to 1.

See it worked

Worked example

A launch has 0.6 chance of £500k and 0.4 chance of −£200k. Find the expected value.

  1. 0.6×500=3000.6 \times 500 = 300.
  2. 0.4×−200=−800.4 \times -200 = -80.
  3. Expected value =£220= £220k.

Answer £220k

Your turn

Question 1Calculator allowed2 marks

Option A costs £50k. It has a 0.7 chance of earning £200k and a 0.3 chance of earning £80k. What is its net gain, in £k?

Question 21 mark

What does a square node represent on a decision tree?

Choose one
Question 32 marks

Give one limitation of decision trees.

Write your answer, then see a model answer
  1. Name the limitation.
  2. Explain it.

Answer Probabilities and values are estimates that may be wrong, and the method ignores non-financial factors and attitudes to risk.

A-level Business Pro, Pearson Edexcel 9BS0

A-level Business Pro

£119 once

Price rises to £199 on 1 January. Save £80 by joining before then.

At least 12 months of access

By paying you agree to our Terms and get access straight away, which ends your 14-day cancellation right.

No VAT is charged.

Independent practice for Pearson Edexcel A-level Business (9BS0), not endorsed by Pearson.

Privacy · Terms